Hey Guys,
We were just informed by the vendor that the shipment for the Pico bodies just arrived earlier in the week after additional unexpected delay. The Pico bodies are currently going through the inspection process, just to be sure the bores are clean and everything is within specification.
The next step for the bodies will be the cartridge heater installation. The next batch of the nozzles are currently in production and expected in the next week. Once they are received, they also need to go through the inspection process to make sure they are clean and made to spec.
As a result of this delay, we are told it to expect the orders to be ready for shipment to everyone in the second week of June. Sorry for the additional delay, and we'll keep everyone updated once we find out more about the status.